How long does a Single Construction Permit permit take in Legacy, Calgary?

Rolling 24 months · Sample: 324
Median days · Applied → Issued
16 days
Sample: 324 permits, last 24 months
Median days · Issued → Completed
188 days
From permit issuance to completion
City-wide median
18 days
Legacy is 2 days faster

Recent examples in Legacy

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14960NewMorrison Homes2026-08-072026-09-0832$400K
BP2026-14952NewMorrison Homes2026-08-072026-09-0832$304K
BP2026-15368NewMorrison Homes2026-08-132026-08-3118$574K
BP2026-14522NewMorrison Homes2026-07-312026-08-3131$390K
BP2026-14509NewJayman Built2026-07-312026-08-2626$311K