How long does a Commercial / Multi Family Project permit take in Legacy, Calgary?
Median days · Applied → Issued
42 days
Sample: 29 permits, last 24 months
Median days · Issued → Completed
165 days
From permit issuance to completion
City-wide median
42 days
Same as Legacy
Recent examples in Legacy
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15861 | Improvement | Okotoks Home Improvements | 2026-08-20 | 2026-09-10 | 21 | $1K |
| BP2026-14225 | New | Kamex Construction | 2026-07-28 | 2026-09-10 | 44 | $480K |
| BP2026-09417 | New | Shane Homes | 2026-05-28 | 2026-08-27 | 91 | $2M |
| BP2026-14613 | New | Shane Homes | 2026-08-04 | 2026-08-26 | 22 | $1.2M |
| BP2026-14608 | New | Shane Homes | 2026-08-04 | 2026-08-26 | 22 | $1.2M |