How long does a Residential Improvement Project permit take in Legacy, Calgary?
Median days · Applied → Issued
14 days
Sample: 408 permits, last 24 months
Median days · Issued → Completed
72 days
From permit issuance to completion
City-wide median
17 days
Legacy is 3 days faster
Recent examples in Legacy
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14947 | New | — | 2026-08-07 | 2026-08-28 | 21 | $42K |
| BP2026-15009 | Improvement | — | 2026-08-09 | 2026-08-27 | 18 | $8K |
| BP2026-16219 | Improvement | — | 2026-08-25 | 2026-08-26 | 1 | $33K |
| BP2026-11022 | New | Spur Renovations | 2026-06-16 | 2026-08-26 | 71 | $47K |
| BP2026-14164 | Improvement | — | 2026-07-27 | 2026-08-20 | 24 | $2K |