How long does a Single Construction Permit permit take in Lake Bonavista, Calgary?
Median days · Applied → Issued
36 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
294 days
From permit issuance to completion
City-wide median
18 days
Lake Bonavista is 18 days slower
Recent examples in Lake Bonavista
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07443 | New | Dnm Contractors | 2026-05-04 | 2026-06-05 | 32 | $1M |
| BP2026-04673 | New | Oldstreet Development | 2026-03-25 | 2026-04-28 | 34 | $702K |
| BP2026-01365 | New | Oldstreet Construction | 2026-01-29 | 2026-03-12 | 42 | $567K |
| BP2025-21685 | New | Brick Developments | 2025-11-07 | 2025-12-03 | 26 | $395K |
| BP2025-21025 | New | Brick Developments | 2025-10-28 | 2025-11-25 | 28 | $394K |