How long does a Demolition permit take in Lake Bonavista, Calgary?

Rolling 24 months · Sample: 5
Median days · Applied → Issued
3 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
18 days
From permit issuance to completion
City-wide median
4 days
Lake Bonavista is 1 days faster

Recent examples in Lake Bonavista

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2025-23301DemolitionA Collaborative Design Group2025-12-062025-12-104$0
BP2025-19723DemolitionWestern One Excavation2025-10-072025-10-092$0
BP2025-16540DemolitionFlintstone Concrete Breakers and Contractors2025-08-252025-08-283$0
BP2025-12974DemolitionCloverhill Construction2025-07-042025-07-073$0
BP2025-07781DemolitionCertified Asbestos Removal and Restoration2025-04-292025-04-301$0