How long does a Commercial / Multi Family Project permit take in Lake Bonavista, Calgary?
Median days · Applied → Issued
33 days
Sample: 27 permits, last 24 months
Median days · Issued → Completed
99 days
From permit issuance to completion
City-wide median
42 days
Lake Bonavista is 9 days faster
Recent examples in Lake Bonavista
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13844 | Improvement | Persimmon Contracting | 2026-07-23 | 2026-08-26 | 34 | $400K |
| BP2026-10088 | Improvement | — | 2026-06-04 | 2026-07-24 | 50 | $30K |
| BP2026-08868 | Improvement | — | 2026-05-20 | 2026-06-22 | 33 | $576 |
| BP2026-02367 | Improvement | Barjac | 2026-02-17 | 2026-06-09 | 112 | $1.3M |
| BP2026-06123 | Improvement | — | 2026-04-16 | 2026-05-20 | 34 | $75K |