How long does a Commercial / Multi Family Project permit take in Lake Bonavista, Calgary?

Rolling 24 months · Sample: 27
Median days · Applied → Issued
33 days
Sample: 27 permits, last 24 months
Median days · Issued → Completed
99 days
From permit issuance to completion
City-wide median
42 days
Lake Bonavista is 9 days faster

Recent examples in Lake Bonavista

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13844ImprovementPersimmon Contracting2026-07-232026-08-2634$400K
BP2026-10088Improvement2026-06-042026-07-2450$30K
BP2026-08868Improvement2026-05-202026-06-2233$576
BP2026-02367ImprovementBarjac2026-02-172026-06-09112$1.3M
BP2026-06123Improvement2026-04-162026-05-2034$75K