How long does a Single Construction Permit permit take in Hounsfield Heights/Briar Hill, Calgary?

Rolling 24 months · Sample: 17
Median days · Applied → Issued
37 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
335 days
From permit issuance to completion
City-wide median
18 days
Hounsfield Heights/Briar Hill is 19 days slower

Recent examples in Hounsfield Heights/Briar Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08071NewMaillot Homes2026-05-112026-09-09121$698K
BP2026-07972NewDouglas Allan2026-05-082026-08-1195$522K
BP2026-07808NewBaidwan Construction2026-05-072026-07-1064$826K
BP2025-22481NewGill Developments2025-11-212026-02-0273$469K
BP2025-23685NewGeneral Home2025-12-152026-01-2238$550K