How long does a Single Construction Permit permit take in Hounsfield Heights/Briar Hill, Calgary?
Median days · Applied → Issued
37 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
335 days
From permit issuance to completion
City-wide median
18 days
Hounsfield Heights/Briar Hill is 19 days slower
Recent examples in Hounsfield Heights/Briar Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08071 | New | Maillot Homes | 2026-05-11 | 2026-09-09 | 121 | $698K |
| BP2026-07972 | New | Douglas Allan | 2026-05-08 | 2026-08-11 | 95 | $522K |
| BP2026-07808 | New | Baidwan Construction | 2026-05-07 | 2026-07-10 | 64 | $826K |
| BP2025-22481 | New | Gill Developments | 2025-11-21 | 2026-02-02 | 73 | $469K |
| BP2025-23685 | New | General Home | 2025-12-15 | 2026-01-22 | 38 | $550K |