How long does a Demolition permit take in Hounsfield Heights/Briar Hill, Calgary?
Median days · Applied → Issued
6 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
48 days
From permit issuance to completion
City-wide median
4 days
Hounsfield Heights/Briar Hill is 2 days slower
Recent examples in Hounsfield Heights/Briar Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15234 | Demolition | Cloverhill Construction | 2026-08-12 | 2026-08-17 | 5 | $0 |
| BP2026-07615 | Demolition | Pezzente Brothers Construction | 2026-05-05 | 2026-08-06 | 93 | $0 |
| BP2026-11712 | Demolition | Graham Construction and Engineering | 2026-06-25 | 2026-07-16 | 21 | $0 |
| BP2026-12957 | Demolition | Creative Solutions Contracting Services | 2026-07-13 | 2026-07-13 | 0 | $0 |
| BP2026-11494 | Demolition | Shemsho Construction | 2026-06-22 | 2026-06-26 | 4 | $0 |