How long does a Demolition permit take in Hounsfield Heights/Briar Hill, Calgary?

Rolling 24 months · Sample: 21
Median days · Applied → Issued
6 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
48 days
From permit issuance to completion
City-wide median
4 days
Hounsfield Heights/Briar Hill is 2 days slower

Recent examples in Hounsfield Heights/Briar Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15234DemolitionCloverhill Construction2026-08-122026-08-175$0
BP2026-07615DemolitionPezzente Brothers Construction2026-05-052026-08-0693$0
BP2026-11712DemolitionGraham Construction and Engineering2026-06-252026-07-1621$0
BP2026-12957DemolitionCreative Solutions Contracting Services2026-07-132026-07-130$0
BP2026-11494DemolitionShemsho Construction2026-06-222026-06-264$0