How long does a Commercial / Multi Family Project permit take in Hounsfield Heights/Briar Hill, Calgary?
Median days · Applied → Issued
29 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
177 days
From permit issuance to completion
City-wide median
42 days
Hounsfield Heights/Briar Hill is 13 days faster
Recent examples in Hounsfield Heights/Briar Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12964 | Unspecified | Sprouse Fire and Safety | 2026-07-13 | 2026-07-17 | 4 | $4K |
| BP2026-09303 | Improvement | Xerri Custom Home Builders | 2026-05-27 | 2026-06-25 | 29 | $60K |
| BP2026-04601 | Unspecified | — | 2026-03-24 | 2026-04-10 | 17 | $3K |
| BP2026-03541 | Improvement | Trimax Construction | 2026-03-09 | 2026-04-08 | 30 | $50K |
| BP2025-23418 | New | Sihota Developments | 2025-12-09 | 2026-03-23 | 104 | $747K |