How long does a Commercial / Multi Family Project permit take in Hotchkiss, Calgary?

Rolling 24 months · Sample: 42
Median days · Applied → Issued
62 days
Sample: 42 permits, last 24 months
Median days · Issued → Completed
288 days
From permit issuance to completion
City-wide median
42 days
Hotchkiss is 20 days slower

Recent examples in Hotchkiss

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-04616Improvement2026-03-252026-09-09168$30K
BP2026-14275NewDouglas Homes2026-07-292026-08-1618$473K
BP2026-09710Improvement2026-05-312026-07-3060$35K
BP2026-09923NewRohit Communities2026-06-022026-07-1543$542K
BP2026-10426NewRohit Communities2026-06-092026-07-0627$541K