How long does a Commercial / Multi Family Project permit take in Hotchkiss, Calgary?
Median days · Applied → Issued
62 days
Sample: 42 permits, last 24 months
Median days · Issued → Completed
288 days
From permit issuance to completion
City-wide median
42 days
Hotchkiss is 20 days slower
Recent examples in Hotchkiss
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-04616 | Improvement | — | 2026-03-25 | 2026-09-09 | 168 | $30K |
| BP2026-14275 | New | Douglas Homes | 2026-07-29 | 2026-08-16 | 18 | $473K |
| BP2026-09710 | Improvement | — | 2026-05-31 | 2026-07-30 | 60 | $35K |
| BP2026-09923 | New | Rohit Communities | 2026-06-02 | 2026-07-15 | 43 | $542K |
| BP2026-10426 | New | Rohit Communities | 2026-06-09 | 2026-07-06 | 27 | $541K |