How long does a Residential Improvement Project permit take in Highwood, Calgary?
Median days · Applied → Issued
27 days
Sample: 48 permits, last 24 months
Median days · Issued → Completed
189 days
From permit issuance to completion
City-wide median
17 days
Highwood is 10 days slower
Recent examples in Highwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06373 | New | — | 2026-04-20 | 2026-08-19 | 121 | $39K |
| BP2025-08435 | Improvement | — | 2025-05-07 | 2026-08-06 | 456 | $74K |
| BP2026-10375 | Improvement | House Crush | 2026-06-08 | 2026-07-15 | 37 | $220K |
| BP2026-08179 | Improvement | — | 2026-05-11 | 2026-06-29 | 49 | $269K |
| BP2026-09080 | Improvement | — | 2026-05-22 | 2026-06-18 | 27 | $23K |