How long does a Demolition permit take in Highwood, Calgary?

Rolling 24 months · Sample: 19
Median days · Applied → Issued
2 days
Sample: 19 permits, last 24 months
Median days · Issued → Completed
34 days
From permit issuance to completion
City-wide median
4 days
Highwood is 2 days faster

Recent examples in Highwood

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14821DemolitionWestern One Excavation2026-08-062026-08-071$0
BP2026-11676DemolitionP and G Excavating Trucking2026-06-242026-06-251$0
BP2026-10952DemolitionHolmes Building Movers2026-06-152026-06-172$0
BP2026-09983DemolitionDynamic Dirt Works2026-06-032026-06-041$0
BP2026-07646DemolitionWestern One Excavation2026-05-052026-06-0228$0