How long does a Commercial / Multi Family Project permit take in Highwood, Calgary?

Rolling 24 months · Sample: 10
Median days · Applied → Issued
77 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
44 days
From permit issuance to completion
City-wide median
42 days
Highwood is 35 days slower

Recent examples in Highwood

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12295NewAllure Luxury Homes2026-07-022026-09-0868$806K
BP2025-16411NewGenex Builder Group2025-08-222026-05-06257$688K
BP2025-22449NewWiz Design and Build2025-11-202026-04-21152$1.2M
BP2026-01888Improvement2026-02-072026-03-1738$40K
BP2025-23269NewBjk Management2025-12-052026-01-1440$605K