How long does a Commercial / Multi Family Project permit take in Highwood, Calgary?
Median days · Applied → Issued
77 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
44 days
From permit issuance to completion
City-wide median
42 days
Highwood is 35 days slower
Recent examples in Highwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12295 | New | Allure Luxury Homes | 2026-07-02 | 2026-09-08 | 68 | $806K |
| BP2025-16411 | New | Genex Builder Group | 2025-08-22 | 2026-05-06 | 257 | $688K |
| BP2025-22449 | New | Wiz Design and Build | 2025-11-20 | 2026-04-21 | 152 | $1.2M |
| BP2026-01888 | Improvement | — | 2026-02-07 | 2026-03-17 | 38 | $40K |
| BP2025-23269 | New | Bjk Management | 2025-12-05 | 2026-01-14 | 40 | $605K |