How long does a Single Construction Permit permit take in Highland Park, Calgary?
Median days · Applied → Issued
43 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
276 days
From permit issuance to completion
City-wide median
18 days
Highland Park is 25 days slower
Recent examples in Highland Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12649 | New | G Star Home | 2026-07-08 | 2026-07-30 | 22 | $197K |
| BP2026-12651 | New | G Star Home | 2026-07-08 | 2026-07-30 | 22 | $197K |
| BP2026-09679 | New | Ss and K Homes | 2026-05-30 | 2026-07-08 | 39 | $322K |
| BP2026-09681 | New | Ss and K Homes | 2026-05-30 | 2026-06-25 | 26 | $323K |
| BP2026-03286 | New | Homes by Icon | 2026-03-04 | 2026-04-23 | 50 | $416K |