How long does a Residential Improvement Project permit take in Highland Park, Calgary?

Rolling 24 months · Sample: 49
Median days · Applied → Issued
34 days
Sample: 49 permits, last 24 months
Median days · Issued → Completed
151 days
From permit issuance to completion
City-wide median
17 days
Highland Park is 17 days slower

Recent examples in Highland Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13703Improvement2026-07-222026-08-2837$0
BP2026-11165ImprovementWestcan Builders2026-06-172026-08-2569$47K
BP2026-11198Improvement2026-06-182026-08-2063$144K
BP2026-12650NewG Star Home2026-07-082026-07-3022$37K
BP2026-12652NewG Star Home2026-07-082026-07-3022$37K