How long does a Residential Improvement Project permit take in Highland Park, Calgary?
Median days · Applied → Issued
34 days
Sample: 49 permits, last 24 months
Median days · Issued → Completed
151 days
From permit issuance to completion
City-wide median
17 days
Highland Park is 17 days slower
Recent examples in Highland Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13703 | Improvement | — | 2026-07-22 | 2026-08-28 | 37 | $0 |
| BP2026-11165 | Improvement | Westcan Builders | 2026-06-17 | 2026-08-25 | 69 | $47K |
| BP2026-11198 | Improvement | — | 2026-06-18 | 2026-08-20 | 63 | $144K |
| BP2026-12650 | New | G Star Home | 2026-07-08 | 2026-07-30 | 22 | $37K |
| BP2026-12652 | New | G Star Home | 2026-07-08 | 2026-07-30 | 22 | $37K |