How long does a Commercial / Multi Family Project permit take in Highland Park, Calgary?

Rolling 24 months · Sample: 37
Median days · Applied → Issued
57 days
Sample: 37 permits, last 24 months
Median days · Issued → Completed
391 days
From permit issuance to completion
City-wide median
42 days
Highland Park is 15 days slower

Recent examples in Highland Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08315NewGood Earth Homes and Developments2026-05-132026-08-1493$271K
BP2026-10586Improvement2026-06-102026-08-0657$450K
BP2026-11450NewEagle Crest Construction2026-06-222026-08-0443$49K
BP2026-10955NewOne Developments Capital2026-06-152026-07-2338$886K
BP2026-06023NewArbutus Rock Asset Management2026-04-152026-07-1692$842K