How long does a Commercial / Multi Family Project permit take in Highland Park, Calgary?
Median days · Applied → Issued
57 days
Sample: 37 permits, last 24 months
Median days · Issued → Completed
391 days
From permit issuance to completion
City-wide median
42 days
Highland Park is 15 days slower
Recent examples in Highland Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08315 | New | Good Earth Homes and Developments | 2026-05-13 | 2026-08-14 | 93 | $271K |
| BP2026-10586 | Improvement | — | 2026-06-10 | 2026-08-06 | 57 | $450K |
| BP2026-11450 | New | Eagle Crest Construction | 2026-06-22 | 2026-08-04 | 43 | $49K |
| BP2026-10955 | New | One Developments Capital | 2026-06-15 | 2026-07-23 | 38 | $886K |
| BP2026-06023 | New | Arbutus Rock Asset Management | 2026-04-15 | 2026-07-16 | 92 | $842K |