How long does a Residential Improvement Project permit take in Haysboro, Calgary?
Median days · Applied → Issued
26 days
Sample: 110 permits, last 24 months
Median days · Issued → Completed
118 days
From permit issuance to completion
City-wide median
17 days
Haysboro is 9 days slower
Recent examples in Haysboro
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12545 | New | Alta Home | 2026-07-07 | 2026-09-09 | 64 | $51K |
| BP2026-14997 | Improvement | — | 2026-08-09 | 2026-09-02 | 24 | $8K |
| BP2026-15337 | New | Alliance Renovations and Concrete | 2026-08-13 | 2026-08-25 | 12 | $42K |
| BP2026-14074 | New | Gecko Projects | 2026-07-27 | 2026-08-19 | 23 | $34K |
| BP2026-13997 | Improvement | — | 2026-07-25 | 2026-08-10 | 16 | $2K |