How long does a Demolition permit take in Haysboro, Calgary?
Median days · Applied → Issued
3 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
47 days
From permit issuance to completion
City-wide median
4 days
Haysboro is 1 days faster
Recent examples in Haysboro
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14256 | Demolition | Cloverhill Construction | 2026-07-28 | 2026-08-11 | 14 | $0 |
| BP2026-12773 | Demolition | Cloverhill Construction | 2026-07-09 | 2026-07-10 | 1 | $0 |
| BP2026-06998 | Demolition | Cloverhill Construction | 2026-04-28 | 2026-05-04 | 6 | $0 |
| BP2026-01891 | Demolition | Shemsho Construction | 2026-02-08 | 2026-02-10 | 2 | $0 |
| BP2025-23123 | Demolition | Shemsho Construction | 2025-12-03 | 2026-01-09 | 37 | $0 |