How long does a Demolition permit take in Haysboro, Calgary?

Rolling 24 months · Sample: 8
Median days · Applied → Issued
3 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
47 days
From permit issuance to completion
City-wide median
4 days
Haysboro is 1 days faster

Recent examples in Haysboro

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14256DemolitionCloverhill Construction2026-07-282026-08-1114$0
BP2026-12773DemolitionCloverhill Construction2026-07-092026-07-101$0
BP2026-06998DemolitionCloverhill Construction2026-04-282026-05-046$0
BP2026-01891DemolitionShemsho Construction2026-02-082026-02-102$0
BP2025-23123DemolitionShemsho Construction2025-12-032026-01-0937$0