How long does a Commercial / Multi Family Project permit take in Haysboro, Calgary?

Rolling 24 months · Sample: 66
Median days · Applied → Issued
52 days
Sample: 66 permits, last 24 months
Median days · Issued → Completed
139 days
From permit issuance to completion
City-wide median
42 days
Haysboro is 10 days slower

Recent examples in Haysboro

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13488New2026-07-202026-09-0345$972K
BP2026-13491New2026-07-202026-09-0345$547K
BP2026-04293NewDeveraux Developments2026-03-202026-08-25158$236K
BP2026-15754ImprovementRamcorr Construction2026-08-192026-08-245$145K
BP2026-11002Improvement2026-06-162026-08-2166$20K