How long does a Single Construction Permit permit take in Haskayne, Calgary?

Rolling 24 months · Sample: 452
Median days · Applied → Issued
18 days
Sample: 452 permits, last 24 months
Median days · Issued → Completed
210 days
From permit issuance to completion
City-wide median
18 days
Same as Haskayne

Recent examples in Haskayne

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15773NewBrookfield Residential2026-08-192026-09-1123$304K
BP2026-15046NewMorrison Homes2026-08-102026-09-0829$281K
BP2026-13636NewLupi Luxury Homes2026-07-212026-08-2838$500K
BP2026-14507NewMorrison Homes2026-07-312026-08-2626$264K
BP2026-14690NewCedarglen Group2026-08-052026-08-2217$424K