How long does a Commercial / Multi Family Project permit take in Haskayne, Calgary?

Rolling 24 months · Sample: 35
Median days · Applied → Issued
21 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
320 days
From permit issuance to completion
City-wide median
42 days
Haskayne is 21 days faster

Recent examples in Haskayne

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16076NewBrookfield Residential2026-08-242026-09-0310$1M
BP2026-08946NewAvalon Master Builder Avalon Industries2026-05-212026-07-2969$161K
BP2026-08380NewBrookfield Residential2026-05-132026-06-3048$118K
BP2025-16525NewAvalon Master Builder Avalon Industries2025-08-252026-06-11290$2.3M
BP2026-05836NewBrookfield Residential2026-04-132026-06-0351$1.5M