How long does a Commercial / Multi Family Project permit take in Haskayne, Calgary?
Median days · Applied → Issued
21 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
320 days
From permit issuance to completion
City-wide median
42 days
Haskayne is 21 days faster
Recent examples in Haskayne
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16076 | New | Brookfield Residential | 2026-08-24 | 2026-09-03 | 10 | $1M |
| BP2026-08946 | New | Avalon Master Builder Avalon Industries | 2026-05-21 | 2026-07-29 | 69 | $161K |
| BP2026-08380 | New | Brookfield Residential | 2026-05-13 | 2026-06-30 | 48 | $118K |
| BP2025-16525 | New | Avalon Master Builder Avalon Industries | 2025-08-25 | 2026-06-11 | 290 | $2.3M |
| BP2026-05836 | New | Brookfield Residential | 2026-04-13 | 2026-06-03 | 51 | $1.5M |