How long does a Residential Improvement Project permit take in Haskayne, Calgary?

Rolling 24 months · Sample: 343
Median days · Applied → Issued
12 days
Sample: 343 permits, last 24 months
Median days · Issued → Completed
60 days
From permit issuance to completion
City-wide median
17 days
Haskayne is 5 days faster

Recent examples in Haskayne

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14610New2026-08-042026-09-0936$46K
BP2026-14609New2026-08-042026-09-0936$46K
BP2026-08232ImprovementUmbrella Construction2026-05-122026-09-04115$100K
BP2026-14988New2026-08-082026-09-0326$74K
BP2026-14728ImprovementGutter Works Exteriors2026-08-052026-08-2823$34K