How long does a Residential Improvement Project permit take in Forest Lawn, Calgary?
Median days · Applied → Issued
22 days
Sample: 56 permits, last 24 months
Median days · Issued → Completed
59 days
From permit issuance to completion
City-wide median
17 days
Forest Lawn is 5 days slower
Recent examples in Forest Lawn
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15249 | New | — | 2026-08-12 | 2026-09-11 | 30 | $142K |
| BP2026-16485 | Improvement | Rizak Concrete Solutions | 2026-08-28 | 2026-09-10 | 13 | $2K |
| BP2026-10714 | Improvement | — | 2026-06-11 | 2026-09-09 | 90 | $2K |
| BP2026-16190 | New | — | 2026-08-25 | 2026-09-09 | 15 | $56K |
| BP2026-15361 | Improvement | Bearcat General Contracting | 2026-08-13 | 2026-08-27 | 14 | $15K |