How long does a Demolition permit take in Forest Lawn, Calgary?
Median days · Applied → Issued
4 days
Sample: 55 permits, last 24 months
Median days · Issued → Completed
56 days
From permit issuance to completion
City-wide median
4 days
Same as Forest Lawn
Recent examples in Forest Lawn
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16490 | Demolition | Done Fast Demolition | 2026-08-28 | 2026-08-31 | 3 | $0 |
| BP2026-16492 | Demolition | Done Fast Demolition | 2026-08-28 | 2026-08-31 | 3 | $0 |
| BP2026-13992 | Demolition | Foundex Ground Services | 2026-07-25 | 2026-08-05 | 11 | $0 |
| BP2026-12307 | Demolition | Singh Developers | 2026-07-02 | 2026-07-09 | 7 | $0 |
| BP2026-10888 | Demolition | Srp Projects | 2026-06-15 | 2026-06-16 | 1 | $0 |