How long does a Demolition permit take in Forest Lawn, Calgary?

Rolling 24 months · Sample: 55
Median days · Applied → Issued
4 days
Sample: 55 permits, last 24 months
Median days · Issued → Completed
56 days
From permit issuance to completion
City-wide median
4 days
Same as Forest Lawn

Recent examples in Forest Lawn

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16490DemolitionDone Fast Demolition2026-08-282026-08-313$0
BP2026-16492DemolitionDone Fast Demolition2026-08-282026-08-313$0
BP2026-13992DemolitionFoundex Ground Services2026-07-252026-08-0511$0
BP2026-12307DemolitionSingh Developers2026-07-022026-07-097$0
BP2026-10888DemolitionSrp Projects2026-06-152026-06-161$0