How long does a Commercial / Multi Family Project permit take in Forest Lawn, Calgary?
Median days · Applied → Issued
88 days
Sample: 77 permits, last 24 months
Median days · Issued → Completed
198 days
From permit issuance to completion
City-wide median
42 days
Forest Lawn is 46 days slower
Recent examples in Forest Lawn
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07809 | New | Mountains Sky Construction | 2026-05-07 | 2026-09-01 | 117 | $417K |
| BP2026-12523 | New | Pro Angle Homes | 2026-07-06 | 2026-09-01 | 57 | $1.3M |
| BP2025-22315 | New | Optima Developments | 2025-11-19 | 2026-08-17 | 271 | $1.3M |
| BP2026-08546 | New | Primeridge Construction | 2026-05-15 | 2026-08-14 | 91 | $962K |
| BP2026-06454 | Improvement | — | 2026-04-21 | 2026-07-24 | 94 | $20K |