How long does a Residential Improvement Project permit take in Erlton, Calgary?

Rolling 24 months · Sample: 7
Median days · Applied → Issued
8 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
94 days
From permit issuance to completion
City-wide median
17 days
Erlton is 9 days faster

Recent examples in Erlton

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-01661Improvement2026-02-032026-02-063$0
BP2026-01667Improvement2026-02-032026-02-063$29K
BP2025-22948ImprovementSandrin Construction2025-12-012026-01-0737$300K
BP2025-18703NewCrafthaven Homes2025-09-232025-10-0916$39K
BP2025-14643New2025-07-282025-08-1518$47K