How long does a Demolition permit take in Erlton, Calgary?
Median days · Applied → Issued
7 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
103 days
From permit issuance to completion
City-wide median
4 days
Erlton is 3 days slower
Recent examples in Erlton
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08701 | Demolition | Cloverhill Construction | 2026-05-19 | 2026-05-28 | 9 | $0 |
| BP2026-08713 | Demolition | Cloverhill Construction | 2026-05-19 | 2026-05-28 | 9 | $0 |
| BP2025-22847 | Demolition | Iron King Excavation | 2025-11-28 | 2025-12-02 | 4 | $0 |
| BP2025-08691 | Demolition | Cloverhill Construction | 2025-05-09 | 2025-05-12 | 3 | $0 |
| BP2024-25130 | Demolition | Raynow Homes | 2024-12-02 | 2024-12-09 | 7 | $0 |