How long does a Commercial / Multi Family Project permit take in Erlton, Calgary?

Rolling 24 months · Sample: 20
Median days · Applied → Issued
40 days
Sample: 20 permits, last 24 months
Median days · Issued → Completed
14 days
From permit issuance to completion
City-wide median
42 days
Erlton is 2 days faster

Recent examples in Erlton

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-05544New2026-04-082026-08-17131$775K
BP2026-05545New2026-04-082026-08-17131$444K
BP2026-11665ImprovementTayo Construction2026-06-242026-08-0744$300K
BP2026-11668ImprovementTayo Construction2026-06-242026-07-3137$300K
BP2025-23089ImprovementMillennium Building and Construction2025-12-032025-12-2522$5K