How long does a Single Construction Permit permit take in Elboya, Calgary?

Rolling 24 months · Sample: 8
Median days · Applied → Issued
54 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
335 days
From permit issuance to completion
City-wide median
18 days
Elboya is 36 days slower

Recent examples in Elboya

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10199NewWilliam Blake Homes2026-06-052026-07-2954$518K
BP2026-02954NewTrickle Creek Custom Homes2026-02-262026-04-2154$478K
BP2025-20911NewAlec Williams Construction2025-10-272026-03-04128$646K
BP2025-22318NewThelo Homes2025-11-192025-12-1829$650K
BP2025-10636NewWilliam Blake Homes2025-06-042025-06-2723$508K