How long does a Residential Improvement Project permit take in Elboya, Calgary?

Rolling 24 months · Sample: 25
Median days · Applied → Issued
28 days
Sample: 25 permits, last 24 months
Median days · Issued → Completed
223 days
From permit issuance to completion
City-wide median
17 days
Elboya is 11 days slower

Recent examples in Elboya

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10200NewWilliam Blake Homes2026-06-052026-07-2954$68K
BP2026-11608NewGecko Projects2026-06-242026-07-2228$77K
BP2026-10924ImprovementWilliam Blake Homes2026-06-152026-07-0217$135K
BP2025-20912NewAlec Williams Construction2025-10-272026-03-04128$59K
BP2026-02052Improvement2026-02-112026-02-2716$15K