How long does a Commercial / Multi Family Project permit take in Elboya, Calgary?
Median days · Applied → Issued
28 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
115 days
From permit issuance to completion
City-wide median
42 days
Elboya is 14 days faster
Recent examples in Elboya
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05818 | Improvement | — | 2026-04-13 | 2026-08-19 | 128 | $1.8M |
| BP2026-10244 | Improvement | Tayo Construction | 2026-06-05 | 2026-06-30 | 25 | $798K |
| BP2026-05169 | Unspecified | — | 2026-04-02 | 2026-04-09 | 7 | $9K |
| BP2025-21493 | Unspecified | — | 2025-11-04 | 2025-12-04 | 30 | $3K |
| BP2025-16589 | Improvement | — | 2025-08-25 | 2025-10-17 | 53 | $13K |