How long does a Commercial / Multi Family Project permit take in Downtown Commercial Core, Calgary?
Median days · Applied → Issued
28 days
Sample: 744 permits, last 24 months
Median days · Issued → Completed
120 days
From permit issuance to completion
City-wide median
42 days
Downtown Commercial Core is 14 days faster
Recent examples in Downtown Commercial Core
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-19912 | Improvement | — | 2026-10-16 | 2026-11-13 | 28 | $200K |
| BP2026-17442 | Improvement | — | 2026-09-11 | 2026-11-12 | 62 | $2M |
| BP2026-16690 | Improvement | — | 2026-09-01 | 2026-11-10 | 70 | $300K |
| BP2026-19628 | Improvement | Royal Construction | 2026-10-13 | 2026-11-06 | 24 | $437K |
| BP2026-19146 | Unspecified | Western Electrical Management | 2026-10-06 | 2026-11-05 | 30 | $12K |