How long does a Commercial / Multi Family Project permit take in Downtown Commercial Core, Calgary?

Rolling 24 months · Sample: 751
Median days · Applied → Issued
27 days
Sample: 751 permits, last 24 months
Median days · Issued → Completed
118 days
From permit issuance to completion
City-wide median
42 days
Downtown Commercial Core is 15 days faster

Recent examples in Downtown Commercial Core

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14924Improvement2026-08-072026-09-1135$123K
BP2026-15889ImprovementGovan Brown & Associates2026-08-202026-09-1021$4.8M
BP2026-16880Improvement2026-09-032026-09-096$183K
BP2026-15666ImprovementXemex Contracting2026-08-182026-09-0922$25K
BP2026-15528Improvement2026-08-162026-09-0924$1K