How long does a Single Construction Permit permit take in Crescent Heights, Calgary?
Median days · Applied → Issued
36 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
204 days
From permit issuance to completion
City-wide median
18 days
Crescent Heights is 18 days slower
Recent examples in Crescent Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13685 | New | Libra Homes | 2026-07-22 | 2026-08-14 | 23 | $464K |
| BP2026-07491 | New | Manor Homes | 2026-05-04 | 2026-08-05 | 93 | $765K |
| BP2026-08885 | New | Cook Custom Homes | 2026-05-20 | 2026-08-05 | 77 | $512K |
| BP2026-11012 | New | Alena Developments | 2026-06-16 | 2026-08-04 | 49 | $0 |
| BP2026-11008 | New | Alena Developments | 2026-06-16 | 2026-07-31 | 45 | $0 |