How long does a Residential Improvement Project permit take in Crescent Heights, Calgary?
Median days · Applied → Issued
23 days
Sample: 44 permits, last 24 months
Median days · Issued → Completed
134 days
From permit issuance to completion
City-wide median
17 days
Crescent Heights is 6 days slower
Recent examples in Crescent Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11013 | New | Alena Developments | 2026-06-16 | 2026-09-10 | 86 | $72K |
| BP2026-11011 | New | Alena Developments | 2026-06-16 | 2026-09-03 | 79 | $72K |
| BP2026-12860 | Improvement | Groundworks | 2026-07-10 | 2026-08-25 | 46 | $15K |
| BP2026-13445 | Improvement | All in Renovations | 2026-07-18 | 2026-08-19 | 32 | $3K |
| BP2026-12743 | New | — | 2026-07-09 | 2026-08-10 | 32 | $55K |