How long does a Commercial / Multi Family Project permit take in Crescent Heights, Calgary?

Rolling 24 months · Sample: 64
Median days · Applied → Issued
43 days
Sample: 64 permits, last 24 months
Median days · Issued → Completed
89 days
From permit issuance to completion
City-wide median
42 days
Crescent Heights is 1 days slower

Recent examples in Crescent Heights

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14089ImprovementDurwest Construction Systems Alberta2026-07-272026-08-1721$68K
BP2025-22907NewMorrison Homes Calgary Multi2025-11-282026-08-14259$22.7M
BP2026-03278NewSunstar Homes2026-03-042026-08-13162$1.9M
BP2026-14697Unspecified2026-08-052026-08-138$2K
BP2026-13543Improvement2026-07-202026-07-244$110K