How long does a Single Construction Permit permit take in Charleswood, Calgary?
Median days · Applied → Issued
69 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
286 days
From permit issuance to completion
City-wide median
18 days
Charleswood is 51 days slower
Recent examples in Charleswood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08956 | New | C and S Dream Homes | 2026-05-21 | 2026-08-18 | 89 | $550K |
| BP2026-08807 | New | — | 2026-05-20 | 2026-07-22 | 63 | $0 |
| BP2026-08963 | New | Cnj Developments | 2026-05-22 | 2026-07-16 | 55 | $563K |
| BP2026-05192 | New | Lusso Custom Homes | 2026-04-02 | 2026-06-01 | 60 | $488K |
| BP2025-20117 | New | Kay 2 Contracting | 2025-10-14 | 2026-01-07 | 85 | $448K |