How long does a Residential Improvement Project permit take in Charleswood, Calgary?
Median days · Applied → Issued
24 days
Sample: 79 permits, last 24 months
Median days · Issued → Completed
136 days
From permit issuance to completion
City-wide median
17 days
Charleswood is 7 days slower
Recent examples in Charleswood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14779 | Improvement | Maxgreen Windows Siding and Roofing | 2026-08-05 | 2026-08-26 | 21 | $1K |
| BP2026-08957 | New | C and S Dream Homes | 2026-05-21 | 2026-08-18 | 89 | $64K |
| BP2026-11936 | Improvement | C Brannon Construction | 2026-06-27 | 2026-07-28 | 31 | $5K |
| BP2026-12425 | New | — | 2026-07-04 | 2026-07-23 | 19 | $74K |
| BP2026-09233 | Improvement | — | 2026-05-26 | 2026-07-07 | 42 | $20K |