How long does a Commercial / Multi Family Project permit take in Charleswood, Calgary?
Median days · Applied → Issued
28 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
32 days
From permit issuance to completion
City-wide median
42 days
Charleswood is 14 days faster
Recent examples in Charleswood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05050 | Improvement | — | 2026-03-31 | 2026-04-15 | 15 | $7K |
| BP2025-21831 | New | Circle Yyc | 2025-11-10 | 2026-02-11 | 93 | $1.1M |
| BP2025-09806 | New | — | 2025-05-26 | 2025-07-16 | 51 | $45K |
| BP2025-09716 | Improvement | Tribuild Contracting | 2025-05-23 | 2025-07-03 | 41 | $160K |
| BP2025-07650 | Improvement | — | 2025-04-28 | 2025-05-13 | 15 | $50K |