How long does a Commercial / Multi Family Project permit take in Charleswood, Calgary?

Rolling 24 months · Sample: 6
Median days · Applied → Issued
28 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
32 days
From permit issuance to completion
City-wide median
42 days
Charleswood is 14 days faster

Recent examples in Charleswood

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-05050Improvement2026-03-312026-04-1515$7K
BP2025-21831NewCircle Yyc2025-11-102026-02-1193$1.1M
BP2025-09806New2025-05-262025-07-1651$45K
BP2025-09716ImprovementTribuild Contracting2025-05-232025-07-0341$160K
BP2025-07650Improvement2025-04-282025-05-1315$50K