How long does a Residential Improvement Project permit take in Capitol Hill, Calgary?

Rolling 24 months · Sample: 66
Median days · Applied → Issued
27 days
Sample: 66 permits, last 24 months
Median days · Issued → Completed
201 days
From permit issuance to completion
City-wide median
17 days
Capitol Hill is 10 days slower

Recent examples in Capitol Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07565ImprovementGk Custom Homes2026-05-042026-08-12100$354K
BP2026-12051Improvement2026-06-292026-07-2223$17K
BP2026-10627NewCustom Home Builders2026-06-102026-07-1434$39K
BP2026-09540NewBonaventure Developments2026-05-292026-07-0840$64K
BP2026-06200NewNewlook Homes2026-04-172026-06-0145$61K