How long does a Demolition permit take in Capitol Hill, Calgary?

Rolling 24 months · Sample: 56
Median days · Applied → Issued
5 days
Sample: 56 permits, last 24 months
Median days · Issued → Completed
32 days
From permit issuance to completion
City-wide median
4 days
Capitol Hill is 1 days slower

Recent examples in Capitol Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16290DemolitionCloverhill Construction2026-08-262026-09-049$0
BP2026-15199DemolitionFoundex Ground Services2026-08-112026-08-2413$0
BP2026-03093DemolitionWestern One Excavation2026-02-282026-06-11103$0
BP2026-08022DemolitionWestern One Excavation2026-05-092026-06-0325$0
BP2026-09598DemolitionWestern One Excavation2026-05-292026-06-024$0