How long does a Commercial / Multi Family Project permit take in Capitol Hill, Calgary?
Median days · Applied → Issued
108 days
Sample: 65 permits, last 24 months
Median days · Issued → Completed
318 days
From permit issuance to completion
City-wide median
42 days
Capitol Hill is 66 days slower
Recent examples in Capitol Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16304 | Unspecified | — | 2026-08-26 | 2026-09-01 | 6 | $12K |
| BP2026-16303 | Unspecified | — | 2026-08-26 | 2026-08-27 | 1 | $15K |
| BP2025-06951 | New | Goaldex | 2025-04-17 | 2026-08-17 | 487 | $766K |
| BP2026-11921 | Improvement | — | 2026-06-26 | 2026-08-12 | 47 | $20K |
| BP2025-17737 | New | — | 2025-09-10 | 2026-08-06 | 330 | $833K |