How long does a Commercial / Multi Family Project permit take in Capitol Hill, Calgary?

Rolling 24 months · Sample: 65
Median days · Applied → Issued
108 days
Sample: 65 permits, last 24 months
Median days · Issued → Completed
318 days
From permit issuance to completion
City-wide median
42 days
Capitol Hill is 66 days slower

Recent examples in Capitol Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16304Unspecified2026-08-262026-09-016$12K
BP2026-16303Unspecified2026-08-262026-08-271$15K
BP2025-06951NewGoaldex2025-04-172026-08-17487$766K
BP2026-11921Improvement2026-06-262026-08-1247$20K
BP2025-17737New2025-09-102026-08-06330$833K