How long does a Single Construction Permit permit take in Bankview, Calgary?
Median days · Applied → Issued
54 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
387 days
From permit issuance to completion
City-wide median
18 days
Bankview is 36 days slower
Recent examples in Bankview
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07344 | New | Willow Haven Designer Homes | 2026-05-01 | 2026-06-29 | 59 | $504K |
| BP2026-07340 | New | Willow Haven Designer Homes | 2026-05-01 | 2026-06-17 | 47 | $508K |
| BP2026-07342 | New | Willow Haven Designer Homes | 2026-05-01 | 2026-06-17 | 47 | $522K |
| BP2025-14406 | New | Newlook Homes | 2025-07-24 | 2025-09-10 | 48 | $360K |
| BP2025-14408 | New | Newlook Homes | 2025-07-24 | 2025-09-10 | 48 | $360K |