How long does a Residential Improvement Project permit take in Bankview, Calgary?

Rolling 24 months · Sample: 35
Median days · Applied → Issued
22 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
218 days
From permit issuance to completion
City-wide median
17 days
Bankview is 5 days slower

Recent examples in Bankview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07345NewWillow Haven Designer Homes2026-05-012026-06-2959$57K
BP2026-10424NewAlliance Renovations and Concrete2026-06-092026-06-2617$51K
BP2026-07341NewWillow Haven Designer Homes2026-05-012026-06-1747$57K
BP2026-07343NewWillow Haven Designer Homes2026-05-012026-06-1747$57K
BP2026-02069Improvement2026-02-112026-03-1936$72K