How long does a Demolition permit take in Bankview, Calgary?

Rolling 24 months · Sample: 12
Median days · Applied → Issued
7 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
183 days
From permit issuance to completion
City-wide median
4 days
Bankview is 3 days slower

Recent examples in Bankview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-06723DemolitionShemsho Construction2026-04-242026-05-017$0
BP2026-00600DemolitionWillow Haven Designer Homes2026-01-152026-01-205$0
BP2026-00657DemolitionWillow Haven Designer Homes2026-01-152026-01-194$0
BP2025-18356DemolitionQ2025-09-182025-12-1790$0
BP2025-18362DemolitionQ2025-09-182025-12-1790$0