How long does a Residential Improvement Project permit take in Albert Park/Radisson Heights, Calgary?
Median days · Applied → Issued
36 days
Sample: 61 permits, last 24 months
Median days · Issued → Completed
186 days
From permit issuance to completion
City-wide median
17 days
Albert Park/Radisson Heights is 19 days slower
Recent examples in Albert Park/Radisson Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15542 | Improvement | — | 2026-08-17 | 2026-09-09 | 23 | $250K |
| BP2026-10240 | Improvement | — | 2026-06-05 | 2026-07-21 | 46 | $0 |
| BP2026-05534 | New | — | 2026-04-08 | 2026-07-02 | 85 | $83K |
| BP2026-07211 | Improvement | — | 2026-04-30 | 2026-07-02 | 63 | $1K |
| BP2026-07213 | Improvement | — | 2026-04-30 | 2026-07-02 | 63 | $1K |