How long does a Commercial / Multi Family Project permit take in Albert Park/Radisson Heights, Calgary?

Rolling 24 months · Sample: 82
Median days · Applied → Issued
53 days
Sample: 82 permits, last 24 months
Median days · Issued → Completed
88 days
From permit issuance to completion
City-wide median
42 days
Albert Park/Radisson Heights is 11 days slower

Recent examples in Albert Park/Radisson Heights

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13606NewHopewell Residential2026-07-212026-09-0950$1.1M
BP2026-11892NewHoneywell Custom Homes2026-06-262026-09-0167$805K
BP2026-12100NewHopewell Residential2026-06-292026-08-1951$2.1M
BP2026-12099NewHopewell Residential2026-06-292026-08-1446$2.1M
BP2026-12096NewHopewell Residential2026-06-292026-08-1143$2.1M