How long does a Demolition permit take in Albert Park/Radisson Heights, Calgary?
Median days · Applied → Issued
5 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
35 days
From permit issuance to completion
City-wide median
4 days
Albert Park/Radisson Heights is 1 days slower
Recent examples in Albert Park/Radisson Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09999 | Demolition | Broch Builders | 2026-06-03 | 2026-06-17 | 14 | $0 |
| BP2026-09177 | Demolition | Delta Excavating and Trucking | 2026-05-25 | 2026-05-28 | 3 | $0 |
| BP2026-05577 | Demolition | Newgen Excavating | 2026-04-09 | 2026-04-20 | 11 | $0 |
| BP2026-05832 | Demolition | Js Construction | 2026-04-13 | 2026-04-15 | 2 | $0 |
| BP2026-02788 | Demolition | Georges Ditching and Trucking | 2026-02-24 | 2026-03-02 | 6 | $0 |