Commercial / Multi Family Project at 5 ST NE

Completed Permit #BP2025-11747 · Renfrew, Calgary

Details

Class
New
Address
5 ST NE
Community
Renfrew
Contractor
General Contractor
Est. project cost
$1.1M
Housing units
3
Applied
2025-06-18
Issued
2025-09-17
Completed
2026-07-28

Description

3-storey, 3-unit rowhouse + 3 SS

Inspection timeline

  1. Progress · Building Deficiencies
    Fail · 2026-07-17
  2. Progress · Building Deficiencies
    Acceptable with Conditions · 2026-07-28
  3. Final · Building Deficiencies
    Acceptable with Conditions · 2026-07-28