How long does a Single Construction Permit permit take in Wolf Willow, Calgary?
Median days · Applied → Issued
19 days
Sample: 285 permits, last 24 months
Median days · Issued → Completed
181 days
From permit issuance to completion
City-wide median
18 days
Wolf Willow is 1 days slower
Recent examples in Wolf Willow
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14867 | New | Jayman Built | 2026-08-06 | 2026-09-10 | 35 | $374K |
| BP2026-15235 | New | Morrison Homes | 2026-08-12 | 2026-09-09 | 28 | $302K |
| BP2026-14757 | New | Morrison Homes | 2026-08-05 | 2026-09-04 | 30 | $273K |
| BP2026-14635 | New | Trico Homes | 2026-08-04 | 2026-09-01 | 28 | $385K |
| BP2026-14199 | New | Morrison Homes | 2026-07-28 | 2026-08-20 | 23 | $278K |