How long does a Commercial / Multi Family Project permit take in Wolf Willow, Calgary?
Median days · Applied → Issued
44 days
Sample: 41 permits, last 24 months
Median days · Issued → Completed
204 days
From permit issuance to completion
City-wide median
42 days
Wolf Willow is 2 days slower
Recent examples in Wolf Willow
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10751 | New | Look Master Builder Calgary | 2026-06-12 | 2026-07-13 | 31 | $105K |
| BP2026-10748 | New | Look Master Builder Calgary | 2026-06-12 | 2026-07-13 | 31 | $105K |
| BP2026-09004 | New | Look Master Builder Calgary | 2026-05-22 | 2026-06-19 | 28 | $800K |
| BP2026-08978 | New | Look Master Builder Calgary | 2026-05-22 | 2026-06-19 | 28 | $800K |
| BP2026-03397 | New | Wolf Willow Park | 2026-03-05 | 2026-06-16 | 103 | $18.5M |